In 2024, Shotcrete Australia was awarded the contract for ground retention works at the Kimbriki Resource Recovery Centre by our valued client, Ward Civil. This project is a key component of the ongoing development at Kimbriki, a leading waste and recycling facility located on Sydney’s Northern Beaches.
The Kimbriki Resource Recovery Centre plays a vital role in waste management and environmental sustainability, providing advanced recycling solutions to reduce landfill waste. As part of its infrastructure improvements, significant ground stabilisation works were required to reinforce embankments and ensure the long-term stability of the site.
Scope of Works: Precision in Ground Engineering
Shotcrete Australia was engaged to stabilise a large embankment within the facility, requiring a combination of soil nails, rock anchoring, and shotcrete applications. Given the complexity of the site, our team executed:
· Installation of over 1,000 soil nails, reaching lengths of up to 4,000mm to reinforce the embankment.
· Application of 2,500m² of shotcrete to create a durable, stabilised surface.
· Ground retention under tight access conditions, requiring meticulous planning and execution.
· Work at height solutions, ensuring safe and efficient installation in challenging terrain.
These essential retention works have reinforced the embankment, providing long-term stability and ensuring the site can continue its operations safely and efficiently.
Overcoming Challenges Through Expertise
The project posed several challenges, including restricted access and the need for precision in high-risk areas. Shotcrete Australia’s highly skilled team and state-of-the-art equipment allowed us to:
· Operate safely within a confined environment, implementing innovative access solutions.
· Deliver works efficiently, keeping the project on schedule.
· Ensure compliance with strict environmental and safety regulations, critical for a site of this nature.
By leveraging our specialist expertise in ground anchoring and shotcreting, we delivered a high-quality, lasting solution while maintaining the highest safety and environmental standards.

A Commitment to Excellence
Shotcrete Australia takes pride in supporting projects that contribute to infrastructure resilience and sustainability. Our work at Kimbriki Resource Recovery Centre is a testament to our ability to deliver complex ground engineering solutions in challenging conditions.
We are proud to have worked alongside Ward Civil to complete this significant ground retention project and look forward to continuing our role in delivering innovative ground engineering solutions across Australia.